Since IPARTs announcement of three new PDRS Battery incentives on 1 July 2026, our team have been swamped with questions about these exciting new activities, the PDRS, PRCs, incentive values and how to get started.
We have compiled a list of some of the most frequently asked questions and answered them below. Please reach out with any other questions and our team will be in touch.
Update 10/08/26: Additional FAQs and updates have been made in all sections below.
Can you claim PRCs if there are existing batteries on site?
PRCs cannot be claimed under BESS1 and BESS3 if there is already a battery storage system on-site. You can claim PRCs under BESS4 and BESS5 if there are existing batteries on-site, provided that no BESS activity has been previously claimed at that site.
Do you require a solar PV system to be installed in order to be eligible?
BESS1 requires a behind-the-meter solar PV system to be installed at the same NMI as the battery system. BESS3, BESS4 and BESS5 do not require a solar PV system to be installed, however, incentives may be higher where a battery is installed within 90 days of a new solar PV system being installed.
How does the PRC market work?
What does PRC historical pricing look like?
The PRC market is governed similarly to the NSW Energy Saving Certificate (ESC) market. Each year, there is a PRC target that is the approximate number of certificates liable entities will have to surrender to meet their obligations. In the event of a market oversupply, depressed pricing is relatively routine, and conversely in periods of undersupply pricing tends to edge towards the tax-effective penalty rate per PRC. This rate is currently set at $2.66, which places the tax effective penalty rate at approximately $3.45.
Historically PRCs have traded as low as $0.90, and as high as $3.60. Given the market is still in a stage of relevant infancy compared to other green markets, and is subject to strong regulatory intervention, PRCs have historically seen significant volatility within the spot and forward markets.
Are projects with Arena funding eligible?
If NSW Government funding has been received for the installation of the new solar PV system, you are not eligible for the higher solar + battery incentive rate. Instead, you must use the lower battery-only incentive rate.
There are no explicit exclusions regarding other federal grants or external funding.
We’re bringing 20MW of capacity online over the coming calendar year. Is there a way to fix the certificate price or lock in a rate?
Currently we are awaiting additional confirmation on the intention of when implementation/activity dates are set, and the DNSP approval requirement.
Both of these requirements have the potential to have a large impact on when PRCs will be able to be registered from a project. Once clarity is gained, a PRC rate is able to be locked in.
Do you have any guidance as yet as to the documentation requirements that we would need to close a project?
At this point in time, the requirements for site and project eligibility are firm however, the exact evidence requirements are still in the process of being finalised. A preliminary list subject to final guides indicates the following will be required:
-
- All planning, development and connection approvals
- Invoice
- Electricity Bill
- Geotagged images of the BESS components, entire system, Solar PV, switchboard and location
- Installer selfies
- Appropriate licences
- Certificate of Compliant Electrical Works (CCEW)
- Nomination Form and consumer fact sheets
What is the definition of “usable battery capacity”?
For BESS3 and BESS5, this is defined as the lesser of:
-
- Usable Battery Capacity; or
- Four hours multiplied by the Battery Inverter Output, or
- 5 kWh per individual dwelling multiplied by the total number of dwellings (BESS3)
- 10,000 kWh (For BESS5)
For BESS4, Battery Capacity is defined as the lesser of:
-
- Usable Battery Capacity; or
- Four hours multiplied by the Battery Inverter Output
‘Usable Battery Capacity’ is defined as 90% of the Nominal Battery Capacity as listed on the CEC Approved Battery list. Battery Capacity is the input used for PRC calculations.
Updated: 10/08/2026
What is the evidence requirement for BESS to be “controllable by a Demand Response Aggregator”?
This requirement needs a BESS to have the ability to be controlled by a DER Aggregator. This can be evidence that the inverter that controls the battery is able to be internet connected and can be controlled. For example, a data sheet or fact sheet showing the make and model of installed battery or inverter, and includes that it is control capable, or an extract from a DRA’s compatible equipment list.
Does “New Solar PV Capacity” refer to AC rating or DC rating?
New Solar PV Capacity refers to DC capacity and is used to determine eligibility, but does not directly affect the PRC calculation.
New Solar PV Capacity must not be less than a quarter of the Usable Battery Capacity (i.e. 90% of the Nominal Battery Capacity as listed on the CEC Approved Battery list.)
If a project is planned now but installation occurs after 1 September, will it qualify?
Yes, provided all PDRS requirements are met at the relevant dates, including:
- the ACP must be accredited for the relevant activity before the implementation date and before being nominated as the capacity holder, and
- ACPs must provide consumer fact sheets with the quotation for activities BESS1, BESS2, BESS3 and BESS4.
Added: 10/08/2026
Will IPART publish a central register of Exempt Energy Programs (EEPs)?
Yes, IPART’s Exempt and low-income energy programs webpage lists approved EEPs. The Home Energy Saver Discounts Program (not the Loans program) is currently the only approved EEP. They will update their website as additional programs are approved.
Added: 10/08/2026
What is the implementation date for batteries?
Implementation Date is defined in the PDRS Rule. For all battery activities (except BESS2) the Implementation Date is the date that the installation of all equipment is completed. This means the date that the battery is fully connected, approved and operational on the network. Being technically commissioned alone is not sufficient. The Implementation Date for activity BESS2 is the date the battery is onboarded with the demand response aggregator.
Added: 10/08/2026
What does “behind the meter” solar batteries mean?
“Behind the meter” is defined in the PDRS Rule as End-User Equipment that is installed and supplies energy to a Site with a National Metering Identifier. This means batteries on the customer side supplying power to a home, business or industrial facility (not front of meter systems, which are connected at the utility side to supply directly to the grid). Only behind the meter battery systems are eligible for incentives under the PDRS.
Added: 10/08/2026
Where can I get information on products I can use?
Batteries installed under activities BESS1, BESS2, BESS3 and BESS4 must be listed on the Clean Energy Council (CEC) Approved Batteries list. Not all batteries listed on the CEC approved batteries meet PDRS Rule requirements. You must also ensure the products you use meet all equipment, eligibility and implementation requirements listed in the relevant activity definitions in the PDRS Rule.
Batteries installed under activity BESS5 do not need to be listed on the CEC Approved Batteries list, but they do need to meet all PDRS Rule requirements, including eligibility, equipment and implementation requirements set out in Activity Definition BESS5 in the PDRS Rule.
Added: 10/08/2026
Can you clarify the 90-day solar installation requirement?
The battery must be installed within (i.e. before or after) 90 days of new solar PV installation to qualify for the higher incentive.
Added: 10/08/2026
Why are the battery requirements so complex?
We recognise some stakeholders feel scheme requirements are complex and add costs and administrative burden. PDRS requirements aim to support safe implementations that manage risks associated with batteries, are fit for purpose and meet customer needs, and promote scheme objectives. These requirements are intended to protect scheme integrity while balancing workability and practicality.
Added: 10/08/2026
How do you determine what a small business site is?
“Small Business Site” is defined in clause 10 of the PDRS Rule. You can provide evidence such as an electricity bill that shows annual electricity consumption/usage is under 100 MWh per year (or an equivalent figure, like average daily usage), that allows for annual consumption to be calculated for the business site where the work took place.
Added: 10/08/2026
Is a finance agreement sufficient for minimum payment evidence?
Not necessarily. The evidence must demonstrate that the original nominator has made the required payment. A deposit is generally the simplest form of evidence. Otherwise, repayments may need to be evidenced until the minimum payment threshold is reached.
Added: 10/08/2026
What are the major compliance issues identified by the NSW Building Commission?
The most common issue is incorrect labelling. Other issues include incorrect backup system arrangements and RCD protection requirements. Labelling continues to be one of the most significant areas of non-compliance identified by regulators across Australia.
Added: 10/08/2026
If a battery is installed indoors, will bollards also be required?
It depends on the location. Installers must undertake a risk assessment. If there is a risk of mechanical damage, additional protection such as bollards may be required. Bollards are not mandatory in every indoor installation.
Added: 10/08/2026
Is there a guideline document showing best-practice battery labelling?
Not currently. The NSW Building Commission is developing training material that will help address this. In the meantime, installers should refer to AS/NZS 5139, which clearly outlines labelling requirements.
Added: 10/08/2026
FAQs for BESS3: Apartment Buildings.
Which buildings are eligible, and which are excluded, under BESS3?
To be eligible for BESS3, the site must be a Class 2 residential building containing a minimum of four individual dwellings.
The following sites are ineligible:
-
- Townhouses or villas
- Sites with existing BESS
How is the incentive capped in relation to building size for BESS3?
Incentives are capped at 5kWh per individual dwelling.
For example, a 12-dwelling building can receive PRCs for up to a 60kWh BESS.
Where should the BESS be installed for BESS3?
The BESS must be installed outdoors in a well-ventilated area.
What does “outdoors” mean for BESS3 apartment battery installations?
The intent is that batteries are not located inside any building. The requirement is based on fire safety considerations developed with stakeholders including Fire and Rescue NSW. Batteries should be installed in open outdoor areas.
Added: 10/08/2026
Do independent garages or carport areas qualify as outdoor locations under BESS3?
It would have to be outside of the apartment building. Independent garages or carport areas may not qualify and will need to meet all appropriate eligibility criteria.
Added: 10/08/2026
What is the mandatory customer co-payment for BESS3?
The customer must make a minimum payment of at least $1,000 (excluding GST) for the battery system, installation, and assessment. This cannot be reimbursed, and no non-cash inducements can be offered to reduce the contribution.
The co-payment does not apply to implementations delivered through a Low-income Energy Program.
FAQs for BESS4: Small & Medium Business.
Is there a difference in the formula between BESS4 and BESS5?
Yes, there are differences in the formulas used for BESS4 and BESS5.
Use our BESS PRC Estimator to calculate and compare the two.
Would the delay in DNSP Approval risk the job passing its expiry date, under BESS4?
We are still working with the NSW Government to clarify whether DNSP pre-approval is sufficient.
Which businesses are eligible, and which are excluded, under BESS4?
Small and medium businesses installing behind-the-meter battery energy storage systems between 20kWh and 200 kWh are eligible.
Residential buildings and Data Centres are ineligible under BESS4.
Under BESS4, can I install a 20kWh BESS and claim PRCs, then 12 months later install another 20kWh BESS and claim PRCs for the second system?
No, BESS installations can only be claimed once per site.
The PDRS Rule does not prohibit an existing battery at the NMI for activities BESS4 or BESS5, however, a previous implementation of either BESS4 or BESS5 must not have been conducted at the site.
Updated: 10/08/2026
Which batteries are eligible for BESS4?
Battery systems must meet the following criteria to be eligible:
-
- Listed on the Clean Energy Council’s approved battery list. For modular systems, eligibility is based on the approval of individual battery modules. This means a combined system does not need to be separately registered, provided each module is on the approved list.
- The battery’s Usable Capacity must not exceed six times the Battery Inverter Output.
- The battery must be internet connectable and controllable by a Demand Response Aggregator to ensure VPP orchestration capability.
- All equipment (excluding inverters installed prior to the installation date) must carry a minimum 10-year warranty that guarantees at least 70% capacity retention 10 years from the installation date.
What is the mandatory customer co-payment for BESS4?
The customer must make a minimum payment of at least $5,000 (excluding GST) for the battery system, installation, and assessment. This cannot be reimbursed, and no non-cash inducements can be offered to reduce the contribution.
If a battery has a nominated capacity of 205 kWh and a usable battery capacity of 195 kWh, should it be considered under BESS4 or BESS5?
A battery with a usable battery capacity of 195 kWh (as defined in the PDRS Rule) would be eligible under BESS4 because the usable battery capacity is less than or equal to 200 kWh.
For BESS5, the usable battery capacity must be above 200 kWh.
Added: 10/08/2026
Can projects be pre-approved before a BESS4 or BESS5 installation proceeds?
No. There is no ‘pre-approval’ for certificate creation in the PDRS. Certificates may only be created when all the scheme requirements have been met. ACPs must hold this evidence at the time of certificate creation (or when entering a pre-registration audit).
Added: 10/08/2026
FAQs for BESS5: Commercial & Industrial.
Can I install a BESS larger than 10MWh, under BESS5?
Yes, the incentive threshold for BESS5 is 10MWh, but up to 30MWh is eligible to be installed, as long as all requirements are also met.
What is the mandatory customer co-payment for BESS5?
There is no co-payment published at this time, and it remains an open question with policy makers
What is the “quarter-capacity” matching rule for solar and battery sizing, under BESS5?
It applies to the total rated DC capacity of new solar PV panels, not the battery inverter. This requirement for BESS3, BESS4 and BESS5 intends that the new solar PV array has sufficient generating capacity to supply at least 25% of the battery’s usable storage capacity.
For example, a 100kWh battery system requires a minimum 25 kW solar PV array connected at the site.
The Usable Battery Capacity must also not be more than 6 times the Battery Inverter Output for activities BESS3, BESS4 and BESS5.
Updated: 10/08/2026
What standards and approvals are required for BESS5?
-
- Development Application (DA)
- Network approvals and compliance with the local DNSP connection and commissioning requirements
- UL 9540A, a standardised testing method used to evaluate the fire and explosion hazards associated with thermal runaway in Battery Energy Storage Systems (BESS)
How is a commercial and industrial site defined under BESS5?
The PDRS Rule does not define commercial and industrial site. To be eligible for PRC creation the site must not be a residential building or a data centre and all other BESS5 requirements must be met.
Added: 10/08/2026
Will UL9540A be mandatory for all levels of a battery system under BESS5?
The PDRS Rule requires that all batteries installed under BESS5 must be tested in accordance with UL9540A.
Added: 10/08/2026
Under BESS4 & BESS5, does the address or the NMI classify as a Site?
A Site is defined as an address or a unique identifier, which can be an NMI. Therefore addresses with multiple NMIs, and with distinct loads, may each have one BESS4 or BESS5 implementation.
For example:
| Address | Business | NMI | BESS | Claim |
| 1555 Retail St Sydney, NSW | Tenant 1 | 123456789 | 150 kWh | Claim 1 – BESS4 |
| Tenant 2 | 987654321 | 500 kWh | Claim 2 – BESS5 | |
| Base Building | 123459876 | 1,000 kWh | Claim 3 – BESS5 |
or
| Address | Business | NMI | BESS | Claim |
| 1555 Industrial St West Sydney, NSW | Business 1 | 123456789 | 150 kWh | Claim 1 – BESS4 |
| 987654321 | 500 kWh | Claim 2 – BESS5 | ||
| 123459876 | 1,000 kWh | Claim 3 – BESS5 |
Please note: Evidence of an NMI being pre-existing and in use may be required for multiple NMI claims. The installation of an NMI for the sole purpose of PDRS utilisation is not within the programs intended scope and should not occur.
Added: 12/10/2026
Nancy Sanjoto | Account Manager, Energy & Carbon Services
Nancy specialises in the federal battery & solar schemes (STCs & PRCs), LGCs under the federal Renewable Energy Target, as well as HEER & IHEAB activities under the NSW ESS program,
Victoria
New South Wales
South Australia
Queensland


